Is my land suitable for a data center?
Most parcels are not, and the reason is almost always power. Here are the four screens a buyer runs first, with the thresholds published in 2026, what land near power has sold for, and what to know before you lease, sell or sign an option.
Sources rechecked in November 2026
Where most parcels fall short
A buyer looks at power first, fiber second and land third. If the nearest high-voltage substation is far away or full, nothing else about the parcel matters. If power is close, zoning decides whether the site can be used and how long that takes.
Use the screens below to see where your parcel stands. If it passes, the next step is a written assessment that a developer would take seriously, not a listing.
The four screens, with published thresholds
| Screen | Published threshold | What it means in practice | Who says so |
|---|---|---|---|
| Transmission voltage | 138 kV to 500 kV substations are the range buyers look for | 230 kV as a floor, with 500 kV seen as stronger | Acres, Jul 27, 2026; Saunders Real Estate, May 22, 2026 |
| Distance to a substation | No substation within 10 miles is treated as a fail | Closer is better: every mile of new line adds cost and permits | Acres, Jul 27, 2026 |
| Distance to carrier fiber | No carrier fiber within about 5 miles is treated as a fail | Two carriers on diverse routes is what an operator wants to see | Acres, Jul 27, 2026 |
| Acreage | 10+ acres for edge sites, 50+ for hyperscale, 100+ ideal for 40 MW or more, up to about 300 | A buyer also wants room for a substation, setbacks and later phases | LandApp (LandGate), Apr 2026, updated Aug 2026 |
These thresholds come from land marketplaces, a land broker and a land data vendor. They describe what buyers ask for; they are not utility rules. Only the utility can tell you whether a substation has room for a new load, and on what date.
Zoning, water and the rezoning path
A parcel zoned for industrial use, or in a district that allows data centers, is worth far more to a buyer than one that needs a rezoning. Rules are tightening: Loudoun County ended by-right approval for data centers on Mar 18, 2025 McGuireWoods, Apr 10, 2025, several Georgia counties adopted moratoriums in 2025 GPB, Oct 22, 2025, and Colleton County, South Carolina adopted a six-month moratorium in 2026 ABC News 4, Jul 11, 2026.
"Approved rezoning" means the county has voted the use onto the parcel and the appeal period has run. The Prince William Digital Gateway rezonings were voided by a court for improper notice, a ruling upheld on Mar 31, 2026 WTOP, Apr 2026, so buyers now check how an approval was reached, not just that it exists.
Water matters if the buyer plans evaporative cooling. A capacity letter from the local water utility helps; high water stress hurts.
What land near power has sold for
| Where | Price per acre | The deal behind it |
|---|---|---|
| Loudoun County, VA | About $6.3M per acre | $615M for 97 acres, SDC Capital, Nov 2025; the county's residential median is about $125,000 per acre |
| Prince William County, VA | About $3.75M per acre | $465.5M for about 124 acres, Microsoft, 2024 |
| Fairfax County, VA | About $4M per acre | Starwood agreement, 2026 |
| North Las Vegas, NV | More than $880,000 per acre | $181M for about 205 acres, Novva and VanTrust, 2025 |
| Texas Route 67 corridor | $350,000+ per acre | Up from $20,000 to $40,000, a market range reported by HousingWire |
Per-acre figures are NAHB's calculations from reported deals: NAHB Eye on Housing, July 2026.
One land data vendor puts land near power at roughly $150,000 to $400,000 per MW of confirmed capacity. Acres, Jul 27, 2026, vendor figure The common thread is confirmed power. Parcels without it rarely see these prices.
Lease, sell or option: the basics
Sell
One payment, and the risk passes to the buyer. You give up any upside if the site gains power later.
Ground lease
Rent over a long term while you keep the land. Your income depends on the tenant, and the land is tied up for decades.
Option
The developer pays to hold the right to buy or lease while it works on power and zoning. Watch the length, the extension fees and what happens to studies and permits if the option lapses.
Before you sign anything
Power can take years: Texas interconnection typically runs 2 to 4 years and Northern Virginia 3 to 5 or more ASHRAE. Make sure the option term and its extensions match that reality, and take legal and tax advice.
What a developer will ask you for
- A deed and parcel map, with any easements and rights of way.
- The zoning designation and any correspondence with the planning department.
- Letters or emails from the electric utility about service to the parcel.
- Any environmental reports, wetlands studies or surveys already done.
- Flood map status for the parcel.
Our land assessment: a fixed fee, in writing
When a parcel looks promising, owners ask us for an assessment a buyer would take seriously. It covers:
- The four screens, measured for your parcel: transmission voltage, substation distance, fiber distance and usable acreage.
- A review of the utility, its large-load rules and any public capacity information for the area.
- The zoning path, with moratorium and ordinance checks at county and city level.
- Flood and natural hazard status from FEMA's maps and National Risk Index.
- A score on the landowner preset, with confidence, and the documents that would raise it.
- A plain recommendation on whether to approach developers now, after specific work, or not at all, and what lease, sale and option terms to weigh.
The assessment is a fixed fee. We quote it by email after reading your request, and work starts only after you approve it in writing. We do not list land or find buyers as part of it.
Landowner questions
How many acres does a data center need?
It depends on the project. One land marketplace puts it at 10 or more acres for an edge site, 50 or more for hyperscale, and 100 or more as ideal for 40 MW and up, with some campuses reaching about 300 acres (LandApp, updated Aug 2026). Buyers also need room for a substation, setbacks and later phases.
How close does a data center need to be to a substation?
As close as possible. One land data vendor treats a parcel with no substation within 10 miles as a fail, and looks for substations from 138 kV to 500 kV (Acres, Jul 27, 2026). Distance alone is not enough: the substation also needs spare capacity, which only the utility can confirm.
Can farmland be used for a data center?
Often, but usually not without a zoning change. Agricultural zoning rarely allows a data center by right, so the buyer needs a rezoning or special permit, and several counties paused approvals in 2025 and 2026. Check the county's current rules before assuming farmland qualifies.
How much do data centers pay per acre?
Prices vary enormously with power. NAHB calculated about $6.3 million an acre for a 2025 Loudoun County deal and more than $880,000 an acre in North Las Vegas, while the Texas Route 67 corridor was reported at $350,000 an acre and up (NAHB, July 2026). Land without a credible power path does not trade at those levels.
Should I lease or sell my land to a data center developer?
Selling ends your exposure and pays once. A ground lease pays over a long term but ties up the land and depends on the tenant. Most deals start with an option: the developer pays to hold the right to buy while it works on power and zoning. The right choice depends on your tax position and how long you can wait, so take legal and tax advice before signing.
What is powered land?
Land with a confirmed path to electric service at data center scale: a load study or utility commitment for a stated MW and date, ideally with zoning in place. One vendor reports land near power trading at roughly $150,000 to $400,000 per MW of confirmed capacity (Acres, Jul 27, 2026).