Data center site selection checklist

Every check in the order it usually happens, from the desktop screen to energization. Knock-outs are marked, and each line names the document that settles it. Download it as a spreadsheet or print it; no email needed.

Sources rechecked in November 2026

How to use this checklist

Work it top to bottom for each candidate. A site that fails a Knock-out check is out, however well it does elsewhere. A Tradeoff check feeds a score: weak results cost points, not the site.

Download the checklist (CSV)

The spreadsheet has columns for three sites, an owner and a due date. It opens in Excel, Google Sheets or Numbers.

Checks for a new build, phase by phase

Desktop screen

CheckTypeEvidence to ask for
Required MW, phases and the latest acceptable energization date written downTradeoffInternal project brief
Transmission lines and substations near each site mapped, with voltageTradeoffUtility or GIS transmission map extract
Moratoriums and pending ordinance changes checked at county and city levelKnock-outPlanning agenda and ordinance search, dated
Hazard ratings pulled for each census tractTradeoffFEMA National Risk Index tract report
Regulatory floodway and flood zone checkedKnock-outFEMA flood map panel
Latency budget tested on real carrier routesKnock-outCarrier route maps and round-trip measurements

Utility and power

CheckTypeEvidence to ask for
Load request submitted, with MW by phaseTradeoffUtility load request acknowledgment
Capacity and date confirmed for the full MWKnock-outLoad study or will-serve letter
Tariff terms read: minimum demand, term, exit fee, collateralTradeoffApplicable tariff sheet or draft electric service agreement
Batch or cluster study timing and deposit confirmedTradeoffUtility or ISO study schedule

Site visit

CheckTypeEvidence to ask for
Access roads, rail, pipelines and neighbors seen in personTradeoffSite visit notes and photos
Carrier entry points and lateral build routes walkedTradeoffCarrier lateral build estimates
Buildable area matches the plan, with setbacksKnock-outConcept site plan against the minimum first phase
CheckTypeEvidence to ask for
Permitted use confirmed for the parcelKnock-outZoning verification letter
Title and easements reviewedTradeoffTitle commitment and ALTA survey
Environmental condition reviewedTradeoffPhase I environmental site assessment
Wetlands delineatedTradeoffWetlands delineation report
Water and sewer capacity confirmed for the cooling designTradeoffWater and sewer capacity letter

Incentives

CheckTypeEvidence to ask for
State sales tax program open, with thresholds the plan clearsTradeoffProgram rules and a pre-application meeting record
Local property tax abatement terms in writingTradeoffDraft abatement or PILOT agreement

Close and energization

CheckTypeEvidence to ask for
Schedule stress-tested at 12, 24 and 36 months of delayTradeoffProject schedule with delay cases
Electric service agreement signed, with collateral postedTradeoffExecuted electric service agreement
Land closed or optioned on terms that match the power dateTradeoffPurchase agreement or option with extension terms

Checks for tenants leasing colocation or a powered shell

When you lease, the provider has already chosen the site. Your job is to confirm that the building delivers what the site promised, on your date.

CheckEvidence to ask the provider for
Delivered power for your suite, with the date it is liveSigned capacity schedule in the lease or order form
The building's own utility service, and how much is spoken forSingle-line diagram and a utility service summary
Carriers in the meet-me room, and how many enter on separate routesCarrier list and building entrance diagram
Latency to your users or your other regionsRound-trip measurements from the building
Cooling design and the rack density it supportsMechanical basis of design
Flood zone and hazard ratings for the building's tractFEMA flood map panel and National Risk Index tract report
Expansion rights next to your spaceRight of first offer or refusal language
Whether you can claim the state sales tax exemption on your equipmentState program rules and the provider's certificate

The scorer's enterprise or colo lease preset weights fiber and latency higher and treats the building's delivered capacity as the power question.

How long the phases take

The desktop screen and site visits take weeks. The utility phase takes as long as the utility takes: published ranges run from 2 to 4 years for Texas interconnection to 3 to 5 years or more in Northern Virginia ASHRAE AI Data Center Framework, site planning, and Texas now studies loads of 75 MW or more in batches, with the first batch's transmission plan expected in fall 2027 Utility Dive, Jun 22, 2026. Run diligence in parallel with the utility phase so it is done before the power answer arrives.

Want someone to work the list with you? We run shortlist reviews and full studies for a fixed fee approved in writing first. Request a Site Review

Checklist questions

What is the first thing to check when selecting a data center site?

Power: the megawatts you need and the date you need them, then whether the utility can meet both. Write those numbers down before you look at a single parcel, because they decide which sites are worth a load request.

Which checklist items are knock-outs?

Five conditions end a site's candidacy: no credible path to the required MW in the project window, an active moratorium covering a project of your size, a regulatory floodway, a lot smaller than the minimum first phase, and a missed hard latency limit. The checklist marks the checks that test each one.

What documents should I ask for during data center site due diligence?

A load study or will-serve letter, the applicable tariff sheet, a zoning verification letter, a title commitment and ALTA survey, a Phase I environmental site assessment, a wetlands delineation, a water and sewer capacity letter, the FEMA flood map panel and National Risk Index tract report, and the incentive program rules. Each appears on the checklist next to the check it settles.

Is there a version for companies leasing colocation or a powered shell?

Yes. The tenant list on this page covers delivered power and its date, the building's utility service, carrier diversity, latency, cooling, hazards, expansion rights and whether you can claim the state sales tax exemption on your equipment.

How does the checklist relate to the scorer?

The scorer ranks sites on what you know today. The checklist is how you turn Unknowns into scores: each line names the document that lets you score a criterion with confidence.