Data center site selection checklist
Every check in the order it usually happens, from the desktop screen to energization. Knock-outs are marked, and each line names the document that settles it. Download it as a spreadsheet or print it; no email needed.
Sources rechecked in November 2026
How to use this checklist
Work it top to bottom for each candidate. A site that fails a Knock-out check is out, however well it does elsewhere. A Tradeoff check feeds a score: weak results cost points, not the site.
The spreadsheet has columns for three sites, an owner and a due date. It opens in Excel, Google Sheets or Numbers.
Checks for a new build, phase by phase
Desktop screen
| Check | Type | Evidence to ask for |
|---|---|---|
| Required MW, phases and the latest acceptable energization date written down | Tradeoff | Internal project brief |
| Transmission lines and substations near each site mapped, with voltage | Tradeoff | Utility or GIS transmission map extract |
| Moratoriums and pending ordinance changes checked at county and city level | Knock-out | Planning agenda and ordinance search, dated |
| Hazard ratings pulled for each census tract | Tradeoff | FEMA National Risk Index tract report |
| Regulatory floodway and flood zone checked | Knock-out | FEMA flood map panel |
| Latency budget tested on real carrier routes | Knock-out | Carrier route maps and round-trip measurements |
Utility and power
| Check | Type | Evidence to ask for |
|---|---|---|
| Load request submitted, with MW by phase | Tradeoff | Utility load request acknowledgment |
| Capacity and date confirmed for the full MW | Knock-out | Load study or will-serve letter |
| Tariff terms read: minimum demand, term, exit fee, collateral | Tradeoff | Applicable tariff sheet or draft electric service agreement |
| Batch or cluster study timing and deposit confirmed | Tradeoff | Utility or ISO study schedule |
Site visit
| Check | Type | Evidence to ask for |
|---|---|---|
| Access roads, rail, pipelines and neighbors seen in person | Tradeoff | Site visit notes and photos |
| Carrier entry points and lateral build routes walked | Tradeoff | Carrier lateral build estimates |
| Buildable area matches the plan, with setbacks | Knock-out | Concept site plan against the minimum first phase |
Legal, zoning, environment
| Check | Type | Evidence to ask for |
|---|---|---|
| Permitted use confirmed for the parcel | Knock-out | Zoning verification letter |
| Title and easements reviewed | Tradeoff | Title commitment and ALTA survey |
| Environmental condition reviewed | Tradeoff | Phase I environmental site assessment |
| Wetlands delineated | Tradeoff | Wetlands delineation report |
| Water and sewer capacity confirmed for the cooling design | Tradeoff | Water and sewer capacity letter |
Incentives
| Check | Type | Evidence to ask for |
|---|---|---|
| State sales tax program open, with thresholds the plan clears | Tradeoff | Program rules and a pre-application meeting record |
| Local property tax abatement terms in writing | Tradeoff | Draft abatement or PILOT agreement |
Close and energization
| Check | Type | Evidence to ask for |
|---|---|---|
| Schedule stress-tested at 12, 24 and 36 months of delay | Tradeoff | Project schedule with delay cases |
| Electric service agreement signed, with collateral posted | Tradeoff | Executed electric service agreement |
| Land closed or optioned on terms that match the power date | Tradeoff | Purchase agreement or option with extension terms |
Checks for tenants leasing colocation or a powered shell
When you lease, the provider has already chosen the site. Your job is to confirm that the building delivers what the site promised, on your date.
| Check | Evidence to ask the provider for |
|---|---|
| Delivered power for your suite, with the date it is live | Signed capacity schedule in the lease or order form |
| The building's own utility service, and how much is spoken for | Single-line diagram and a utility service summary |
| Carriers in the meet-me room, and how many enter on separate routes | Carrier list and building entrance diagram |
| Latency to your users or your other regions | Round-trip measurements from the building |
| Cooling design and the rack density it supports | Mechanical basis of design |
| Flood zone and hazard ratings for the building's tract | FEMA flood map panel and National Risk Index tract report |
| Expansion rights next to your space | Right of first offer or refusal language |
| Whether you can claim the state sales tax exemption on your equipment | State program rules and the provider's certificate |
The scorer's enterprise or colo lease preset weights fiber and latency higher and treats the building's delivered capacity as the power question.
How long the phases take
The desktop screen and site visits take weeks. The utility phase takes as long as the utility takes: published ranges run from 2 to 4 years for Texas interconnection to 3 to 5 years or more in Northern Virginia ASHRAE AI Data Center Framework, site planning, and Texas now studies loads of 75 MW or more in batches, with the first batch's transmission plan expected in fall 2027 Utility Dive, Jun 22, 2026. Run diligence in parallel with the utility phase so it is done before the power answer arrives.
Want someone to work the list with you? We run shortlist reviews and full studies for a fixed fee approved in writing first. Request a Site Review
Checklist questions
What is the first thing to check when selecting a data center site?
Power: the megawatts you need and the date you need them, then whether the utility can meet both. Write those numbers down before you look at a single parcel, because they decide which sites are worth a load request.
Which checklist items are knock-outs?
Five conditions end a site's candidacy: no credible path to the required MW in the project window, an active moratorium covering a project of your size, a regulatory floodway, a lot smaller than the minimum first phase, and a missed hard latency limit. The checklist marks the checks that test each one.
What documents should I ask for during data center site due diligence?
A load study or will-serve letter, the applicable tariff sheet, a zoning verification letter, a title commitment and ALTA survey, a Phase I environmental site assessment, a wetlands delineation, a water and sewer capacity letter, the FEMA flood map panel and National Risk Index tract report, and the incentive program rules. Each appears on the checklist next to the check it settles.
Is there a version for companies leasing colocation or a powered shell?
Yes. The tenant list on this page covers delivered power and its date, the building's utility service, carrier diversity, latency, cooling, hazards, expansion rights and whether you can claim the state sales tax exemption on your equipment.
How does the checklist relate to the scorer?
The scorer ranks sites on what you know today. The checklist is how you turn Unknowns into scores: each line names the document that lets you score a criterion with confidence.