Data center power availability by market
Eight US markets in one dated table: the utility, its large-load terms, published waits, vacancy, the state sales tax exemption and local limits. Every cell carries its source. Where our sources say nothing, the cell says so.
Sources rechecked in November 2026
Eight markets, side by side
Read across a row to see why a market is easy or hard to build in today. On a phone, each market reads as its own block.
| Market | Utility and grid | Large-load terms | Wait or queue | Vacancy | State sales tax exemption | Local rules and limits |
|---|---|---|---|---|---|---|
| Northern Virginia | Dominion Energy, PJM | GS-5 class from Jan 1, 2027 for loads of 25 MW or more: minimum demand covers at least 85% of T&D and 60% of generation costs, 14-year contracts Inside Climate News on the SCC order, Nov 2025 | Ashburn grid connections 5 to 7 years DC Byte via DCK, Aug 5, 2026 | 0.3% (Q1 2026) CBRE, Jun 17, 2026 | Exemption active: $150M and 50 jobs, through Jun 30, 2035 VEDP | Loudoun moved data centers to special exception on Mar 18, 2025 McGuireWoods, Apr 10, 2025Digital Gateway rezonings voided, upheld on appeal Mar 31, 2026 WTOP, Apr 2026 |
| Columbus, Ohio | AEP Ohio, PJM | Data Center Tariff for loads of 25 MW or more: 85% minimum demand, ramp up to 4 years plus 8, exit fee of 36 months, 50% collateral AEP Ohio, in effect Jul 23, 2025 | Studied in tranches; the latest applications were due Sep 30, 2026 AEP Ohio | 0.1% JLL, Aug 11, 2026; JLL counts differently from CBRE | Not checked for this table | Not in our sources |
| Atlanta | Georgia Power | Over 100 MW: contracts up to 15 years with minimum billing, each reviewed by the PSC Georgia PSC, Jan 23, 2025 | Large-load pipeline grew from 12 GW to 36.5 GW during 2024 DatacenterDynamics, Jan 2025 | 1.0% (Q1 2026); 2,882 MW under construction, now CBRE's largest North American construction market CBRE, Jun 17 and Aug 27, 2026 | Exemption active, thresholds by county size; certificates expire Dec 31, 2031 Ga. Comp. R. & Regs. 560-12-2-.117 | Moratoriums in 2025 in Coweta, Clayton, Pike, Lamar and Troup Counties and LaGrange; Forsyth bars cooling from the county water system GPB, Oct 22, 2025 |
| Dallas-Fort Worth | ERCOT | Batch Zero study rules for loads of 75 MW or more approved Jun 18, 2026; SB 6 large-load rules due by Dec 2026 Utility Dive, Jun 22, 2026; Latitude Media, Dec 3, 2025 | More than 438 GW of large-load requests in the ERCOT queue; interconnection typically 2 to 4 years Utility Dive, Jun 22, 2026; ASHRAE | 1.8% (Q1 2026) CBRE, Jun 17, 2026 | Exemption active: $200M, 20 jobs, 10 or 15 years, state 6.25% only Texas Comptroller, Jul 27, 2026 | Not in our sources |
| West Texas | ERCOT | Same ERCOT batch process as above | Same ERCOT queue as above | Not reported; 2.9 GW under construction (H2 2025) Cushman & Wakefield, Feb 26, 2026 | Same Texas program as above | Water: 58.8% of Texas AI data centers sit in high water stress areas TRG Datacenters via DCK, Oct 12, 2026, vendor analysis |
| Chicago | ComEd, PJM | Not in our sources | Power delivery timelines extend into 2032 or later CBRE, Jun 17, 2026 | 2.2% (Q1 2026); no contiguous 5 MW+ space available in 2026 CBRE, Jun 17 and Aug 27, 2026 | CBRE's H1 2026 Chicago page lists state incentives as paused CBRE, Aug 27, 2026 | Not in our sources |
| Phoenix | APS and SRP | Not in our sources | Not in our sources | Not reported. 442 MW absorbed and 1.7 GW under construction in H1 2026 JLL, Aug 11, 2026260+ MW absorbed in H1 2026, average lease term 7 years CBRE, Aug 27, 2026 | June 2026 budget deal includes a three-year pause for new data centers AZFamily, Jun 9, 2026 | Phoenix has required a Special Permit since Jul 2, 2025 City of PhoenixTucson ended staff work on Project Blue Aug 6, 2025 AZFamily |
| Silicon Valley | PG&E and Silicon Valley Power | Not in our sources | Some developers were told they would not get utility power for over a decade CBRE, Jun 24, 2024 | Asking rents for 10+ MW flat in H1 2026 CBRE, Aug 27, 2026 | Not checked for this table | Not in our sources |
JLL and CBRE measure vacancy differently; compare figures from the same source only. Utility names without a source are given for orientation, not as a statement about capacity.
The national picture
- Primary-market vacancy hit a record low of 1.4% in the first half of 2026, with 7,481 MW under construction and 80.4% of it preleased. CBRE North America Data Center Trends H1 2026, Aug 27, 2026
- Less than 1,500 MW of future colocation capacity in primary markets was still uncommitted, roughly half a year of demand at the current pace. CBRE, Aug 27, 2026
- JLL counted a record 25 GW absorbed in the first half of 2026 and expects vacancy near zero through 2028. JLL, Aug 11, 2026
- Cushman & Wakefield does not expect meaningful easing before 2030. Cushman & Wakefield, Feb 26, 2026
- On the supply side, 2,061 GW of generation and storage was waiting to connect at the end of 2025, and the median project took more than 5 years from request to operation. Lawrence Berkeley National Laboratory, Jul 1, 2026
How to use a market table on a real site
A market row tells you the odds, not the answer for a parcel. Two sites in the same county can sit on different substations with very different capacity. Use the table to decide where to file load requests, then score each site on what the utility tells you. The tariff section and the tax section on the home page explain how to score those criteria.
Leasing rather than building? Vacancy and asking rents matter more than tariffs. CBRE's asking rents for 250 to 500 kW in Northern Virginia ran $190 to $235 per kW per month in Q1 2026, and $200 to $230 in Chicago. CBRE, Jun 17, 2026 We place buyers in colocation and powered shells, and the facility pays our fee. Request a Site Review
What this table leaves out
We left out markets where our sources were too thin to fill most of a row, and figures we could not trace to a primary source. Water stress appears only where a dated source gave it. If you need a market that is not here, the site review request is the place to ask.
Questions about power by market
Where is power available for data centers right now?
Nowhere is it quick at scale. Published ranges run from typically 2 to 4 years for interconnection in Texas (ASHRAE) to 5 to 7 years for grid connections in Ashburn (DC Byte via Data Center Knowledge, Aug 5, 2026), and ComEd's delivery timelines in the Chicago market reach into 2032 or later (CBRE, Jun 17, 2026). Sites that can use existing grid capacity take about half as long as those needing new transmission (CBRE, Sep 9, 2024).
What is the data center vacancy rate in Northern Virginia?
CBRE put Northern Virginia vacancy at 0.3% in Q1 2026, down from 0.8% a year earlier (CBRE Global Data Center Trends 2026, Jun 17, 2026). Across primary North American markets, CBRE reported a record low of 1.4% in the first half of 2026.
Which states paused data center tax incentives?
Arizona's June 2026 budget deal includes a three-year pause on exemptions for new data centers (AZFamily, Jun 9, 2026). CBRE's first-half 2026 Chicago report lists Illinois incentives as paused. Texas, Virginia and Georgia programs remain open, with Georgia certificates expiring Dec 31, 2031.
Why do CBRE and JLL vacancy figures differ?
They measure different things. JLL includes owner-occupied and frontier capacity in its counts, so its figures should not be mixed with CBRE's in one comparison. The table names the source for every vacancy figure.
How often is this table updated?
We check it each quarter and after major tariff, tax or zoning decisions. The date at the top of the page shows the last check.