Data center site selection criteria, scored against your shortlist

Ten criteria decide where a data center can go, and power now outweighs the other nine. Rate each candidate against written anchors, see which ones fail a knock-out, and learn how much of your ranking rests on things nobody has confirmed yet.

For developers, hyperscale and enterprise buyers, investors, and landowners asking whether their acreage could carry a data center.

Reporters at Fortune, Light Reading, Inc. and Al Jazeera have quoted the team that runs this desk.

Illustrative scores, not ratings of real places.Balanced weights

Score and compare your sites

Name your candidates, pick the kind of project, then rate each site from 1 to 5 against written anchors. Unknown is a valid answer. You get a ranked score out of 100, a confidence figure for each site and any knock-outs, without signing up.

Step 1

Which sites are you comparing?

Name two to five. A market, a parcel, a building or a provider all work. Names stay in this browser.

Name your sites to place them on the sheet.Balanced weights

How the scorer reaches a number

Each criterion carries a weight, and the weights add up to 100. You score every site from 1 to 5 against the anchor sentences shown for that criterion. A 5 earns the criterion's full weight, a 4 earns three quarters of it, a 3 half, a 2 a quarter and a 1 nothing. Add those up and you have a score out of 100.

Unknown is allowed, and it costs you. An Unknown counts as a 1, so it earns nothing, and it lowers the site's confidence: the share of the total weight that rests on a score you actually know. A site that leads at 45% confidence is leading on guesses.

Knock-outs sit above the ranking. Five conditions end a site's chances whatever else it scores: no credible path to the megawatts, a moratorium covering a project of your size, a regulatory floodway, a lot smaller than the first phase, or a missed hard latency limit. A site with one of them stays in the list, marked as failing the gate.

The sensitivity line tests your leader. It reruns the ranking with the power weight 10 points higher and 10 points lower, and with every Unknown scored as a 3. If the leader changes under any of those, you know where to spend the next week of diligence.

Every anchor is written down
Each of the 50 scoring levels has a sentence you can test against a document, shown before you pick a score.
Every figure has a source and a date
Printed beside the number. Vendor figures are marked as vendor figures, and figures we could not trace to a primary source are left out.
The scorer sells nothing
No site, utility or developer pays to rank. What you type is kept on your own device, and we see it only if you submit a review request.

Power availability and timeline

Can the utility deliver the megawatts you need, in the phases you need them, by the date your project needs them? Every other criterion assumes the answer is yes, which is why this one carries a quarter of the balanced weight and is the first knock-out.

What to check

  • The voltage and spare capacity of the nearest transmission substation, and whether new lines or a new substation are needed.
  • Whether the utility studies large loads one at a time, in batches or in clusters, and when the next window closes.
  • The energization date for each phase, not just the first one.
  • Whether generation in the region is keeping up with load. New supply is slow: the median generation project took more than 5 years from request to operation, and only 13% of capacity requested from 2000 to 2020 had come online by the end of 2025 (Lawrence Berkeley National Laboratory, Queued Up, Jul 1, 2026).

Evidence to ask for

A load study, or better, a will-serve letter stating MW and dates. Then the study schedule, the deposit that holds your place, and the draft electric service agreement.

Where it stands in 2026

  • ERCOT's large-load queue passed 438 GW of requests, nearly 90% from data centers. Texas regulators approved "Batch Zero" study rules for loads of 75 MW or more on Jun 18, 2026, with a final transmission plan for the batch expected in fall 2027. Utility Dive, Jun 22, 2026
  • Grid connections in Ashburn run 5 to 7 years, against 5.6 GW live and a 15 GW pipeline. DC Byte index, via Data Center Knowledge, Aug 5, 2026
  • ComEd's power delivery timelines in the Chicago market reach into 2032 or later. CBRE Global Data Center Trends 2026, Jun 17, 2026
  • Projects that can use existing grid capacity take about half as long as those waiting on new transmission or interconnection. CBRE, Sep 9, 2024

Permitting, zoning and community

Data centers used to be allowed by right across much of Northern Virginia. That is no longer a safe assumption anywhere. Score the path to an approved use, and the odds that local politics change the rules while you are on it.

What to check

  • Whether the use is permitted by right, by special exception or special permit, or only after rezoning.
  • Moratoriums and draft ordinances at both the county and the city, with their end dates.
  • Noise limits, buffers and size categories in recent ordinances, which can shrink a site's usable area.
  • Whether nearby residents have organized, and how recent approvals in the jurisdiction went.

Evidence to ask for

A zoning verification letter that names the permitted use, the planning department's current agenda, and minutes from the last two data center hearings.

Where it stands in 2026

  • Loudoun County's board voted 7 to 2 on Mar 18, 2025 to make data centers a special exception use in the districts where they had been allowed by right. McGuireWoods, Apr 10, 2025
  • The Prince William Digital Gateway rezonings, covering about 2,000 acres, were voided for improper notice; the Virginia Court of Appeals upheld that on Mar 31, 2026. WTOP, Apr 2026
  • Georgia counties including Coweta, Clayton, Pike, Lamar and Troup adopted moratoriums in 2025, and Bartow set 65 dB day and 55 dB night noise caps. GPB, Oct 22, 2025
  • Phoenix now allows data centers only with a Special Permit that reviews grid reliability, fire risk, emergency access and noise. City of Phoenix, Jul 2, 2025
  • In a national survey, 79% of Americans backed US leadership in AI, but only 14% supported a data center near them. JLL, Aug 11, 2026

Power cost and tariff terms

The energy rate is only part of what power costs you. Large-load tariffs now set minimum bills, long terms, exit fees and collateral, and on a slow ramp those terms can cost more than the rate itself.

What to check

  • The all-in delivered cost per kWh at your load factor, with transmission charges and riders included.
  • The minimum demand percentage, the contract term, the exit fee and the collateral rule.
  • Whether the minimum bill starts at contract signing or follows a ramp schedule that matches your phases.

Evidence to ask for

The tariff sheet that would apply, a draft electric service agreement, and an all-in cost estimate from the utility at your load profile.

Where it stands in 2026

TariffApplies toMinimum billTermCollateral or costSource
AEP Ohio Data Center TariffLoads of 25 MW or more85% of the highest monthly billing demandRamp period of up to 4 years, plus 8 years; exit fee of 36 months of minimum charges50% of total minimum charges, unless rated A-/A3 with enough cashAEP Ohio tariff page (adopted Jul 9, 2025, in effect Jul 23, 2025)
Dominion Energy GS-5 class, VirginiaLoads of 25 MW or more at a 75% load factorAt least 85% of transmission and distribution and 60% of generation costs14-year contracts, starting Jan 1, 2027Not stated in our sourceInside Climate News on the Virginia SCC order (approved Nov 2025)
Georgia Power large-load ruleOver 100 MWMinimum billing in each contractUp to 15 years (was 5); each contract reviewed by the Georgia PSCSite-specific and upstream costs can be billed to the customerGeorgia PSC media advisory, Jan 23, 2025

CBRE's 2024 cost comparison put Atlanta, Northern Virginia, Dallas, Phoenix and Chicago among the lowest-cost markets for electricity, and Silicon Valley, Southern California, the New York Tri-State area, Hillsboro and Minneapolis among the highest. CBRE, Sep 9, 2024

Land, building and site fit

Does the site hold the whole plan, including the substation yard, setbacks and the later phases? For a lease, read this as the building: delivered capacity, floor loading and room to grow.

What to check

  • Buildable acres after wetlands, slopes, easements and setbacks, measured against the minimum first phase and the full build.
  • Title exceptions, pipelines and transmission easements that cross the buildable area.
  • Road access for construction traffic and heavy deliveries.

Evidence to ask for

A title commitment and ALTA survey, a wetlands delineation, and a Phase I environmental site assessment.

Where it stands in 2026

  • Data center land sales reached about $3.3 billion in Q1 2026, up 141%, about 30% of all spending on development sites. Avison Young data, via Bisnow, May 28, 2026
  • Reported deals in Loudoun County worked out to about $6.3 million an acre, against a residential median near $125,000. NAHB, July 2026

Natural hazard risk

Score the asset's exposure, not the community's. FEMA's National Risk Index covers 18 natural hazards by county and census tract, from riverine and coastal flooding to earthquake, hurricane, tornado and wildfire. Its composite Risk Index multiplies expected annual loss by a community risk factor that includes social vulnerability, which describes the people nearby rather than your building. Use the expected annual loss and the rating for each hazard instead.

What to check

  • The tract's expected annual loss rating and its rating for each hazard that could reach the building.
  • The FEMA flood map panel, and whether any part of the parcel is in a regulatory floodway.
  • Hazards to the power and fiber routes feeding the site, not just the parcel.

Evidence to ask for

The National Risk Index tract report, a floodplain determination and, in seismic areas, a geotechnical report.

FEMA National Risk Index, frequently asked questions (data version 1.19.0)

Tax incentives

Sales tax on servers and electrical gear is a large line in any build, so state exemptions move the numbers. They also change. Score what the program offers this project, in this county, during your investment window.

What to check

  • Investment, job and wage thresholds, and whether they vary by county population.
  • Whether the program is open to new applicants, paused, or ending before your spend lands.
  • Local property tax abatements and what they ask for in return.

Evidence to ask for

The current program rules, a record of a pre-application meeting with the state, and a draft abatement agreement from the county.

Where it stands in 2026

The National Conference of State Legislatures counts 38 states with data center tax incentives; all of them waive sales tax on essential equipment, 14 also exempt electricity, and 11 offer partial property tax abatement. NCSL, Apr 9, 2026 Good Jobs First counts 36 states with sales and use tax exemptions and found only 11 disclose recipients. Good Jobs First, via The Register, Nov 11, 2025 The two use different counting methods.

StateThresholdsTerm and statusSource
Texas100,000+ sq ft single occupant, $200M+ invested within 5 years, 20 qualifying jobs in the county10 years ($200M to $250M) or 15 years ($250M+); covers only the 6.25% state sales taxTexas Comptroller, page modified Jul 27, 2026
Virginia$150M capital investment and 50 new jobs at 150% of the local prevailing wage; $70M and 10 jobs in distressed localitiesRuns through Jun 30, 2035, with extensions to 2040 or 2050 for far larger commitmentsVirginia Economic Development Partnership
GeorgiaCounty over 50,000 people: $250M and 25 jobs; 30,001 to 50,000: $75M and 10 jobs; 30,000 or fewer: $25M and 5 jobs; wages at least 110% of the county averageAll certificates expire Dec 31, 2031Ga. Comp. R. & Regs. 560-12-2-.117
ArizonaBefore the pause: $25M or $50M minimum investment depending on county populationJune 2026 budget deal includes a three-year pause on exemptions for new data centers; existing recipients unaffectedAZFamily, Jun 9, 2026

CBRE's Chicago market page for the first half of 2026 lists Illinois incentives as paused. CBRE, Aug 27, 2026

Fiber and carrier diversity

Count carriers, then check that their routes are truly separate. Two carriers in one conduit across one bridge are one failure away from none.

What to check

  • Carriers on the site or at its edge, and the lateral build distance to each of the others.
  • Whether the two entrance routes share a conduit, a crossing or a right of way.
  • Build lead times, which can outlast the building schedule.

Evidence to ask for

Route maps and written lateral build estimates, with cost and lead time, from each carrier.

Where it stands in 2026

More than 20,000 route miles of new fiber were announced in 2026. CBRE North America Data Center Trends H1 2026, Aug 27, 2026 A land data vendor treats a site with no carrier fiber within about 5 miles as a fail. Acres, Jul 27, 2026

Water and cooling

Water need depends on the cooling design, so settle the design before you score. A closed-loop or air-cooled plan asks far less of the local utility than evaporative cooling.

What to check

  • Water stress in the basin, and the utility's capacity at your peak daily draw and discharge.
  • Local rules on cooling water, such as limits on drawing from the public system.

Evidence to ask for

A capacity letter from the water and sewer utility, and the cooling basis of design.

Where it stands in 2026

  • US data centers directly consumed about 17 billion gallons of water in 2023, 84% of it at hyperscale and colocation sites; hyperscale use is projected at 16 to 33 billion gallons a year by 2028. LBNL 2024 United States Data Center Energy Usage Report, via Pew Research Center, Oct 24, 2025
  • Forsyth County, Georgia bars data centers from cooling with county water. GPB, Oct 22, 2025
  • Tucson's city council voted unanimously on Aug 6, 2025 to end staff work on Project Blue, a 290-acre data center, over water and energy concerns. AZFamily, Aug 6, 2025

Latency to users or other regions

Round trip grows by about a millisecond for every 100 km of fiber path, because light in glass needs about 5 microseconds per kilometer, and switching gear adds its own delay on top. CommScope, Latency in optical fiber systems, Feb 2017 Carrier routes bend around rivers, rail lines and property lines, so time real paths rather than map distance. A training cluster can sit far from users; an inference region or a trading system cannot.

What to check

  • A written latency budget for each workload: training, inference, replication and user traffic.
  • Round-trip times on actual carrier routes to the hubs and regions that matter.

Evidence to ask for

Carrier route maps and measured round-trip times from the building or the nearest carrier hut.

Labor and construction access

Large projects draw on the same electricians, linemen and commissioning crews. Score the depth of the local pool against what else is being built nearby during your window.

What to check

  • Competing large projects in the region and their construction schedules.
  • Distance to electrical equipment suppliers and generator service depots.
  • The operations staff you will need once the building is live, and where they will come from.

Where it stands in 2026

Cushman & Wakefield counted 25.3 GW under construction across the Americas at the end of 2025, including 6.3 GW in Virginia and 2.9 GW in West Texas. Cushman & Wakefield, Feb 26, 2026 Atlanta had 2,882 MW under construction in the first half of 2026. CBRE, Aug 27, 2026

How the weights change by project type

The same ten criteria matter for every project, but not equally. The balanced column follows our default method. The other columns are our judgment, offered as starting points; change any of them in the scorer.

CriterionBalancedAI training campusEnterprise or colo leaseInvestor or powered shellLandowner screen
Power availability and timeline2535152540
Permitting, zoning and community151552020
Power cost and tariff terms10121212Not scored
Land, building and site fit107121315
Natural hazard risk8695Not scored
Tax incentives86910Not scored
Fiber and carrier diversity7512515
Water and cooling798410
Latency to users or other regions52123Not scored
Labor and construction access5363Not scored
Total100100100100100
  • AI training campus. Power climbs to 35 and tariff terms to 12, because a slow ramp under a minimum bill is expensive. Latency falls to 2: training runs do not care how far away the users are. More on the AI site selection page.
  • Enterprise or colo lease. Fiber and latency rise to 12 each. Power drops to 15 because you are judging the building's delivered capacity and date, and permitting to 5 because the provider carries it.
  • Investor or powered shell. Entitlement rises to 20 and land to 13, because those are what a tenant pays for.
  • Landowner screen. Power takes 40, and tax, labor, hazard, latency and tariff drop out, since a buyer judges those for its own project. See is my land suitable for a data center.

The site selection process, step by step

  1. Desktop screen

    Write down the MW, the phases and the latest acceptable power date. Map transmission, check moratoriums, pull hazard ratings and test latency. Most candidates drop out here.

  2. Utility engagement

    File load requests for the survivors and ask about study timing, tariff terms and deposits. This step sets the schedule for everything after it.

  3. Site visits

    Walk the parcels, the carrier routes and the access roads. Check that the buildable area matches the plan.

  4. Diligence

    Zoning verification, title, survey, environmental, wetlands, water capacity and incentives, in parallel where possible.

  5. Close and energize

    Sign the electric service agreement, post collateral, and close or option the land on terms that match the power date.

Published timelines for those steps vary widely by market, which is why the power date belongs in the score:

StepPublished rangeSource
How far ahead hyperscalers lock up power and land24 to 36 months before deliveryDC Byte, via BetaNews, Nov 27, 2025
Utility queue position for a new loadAbout six monthsRamboll, Dec 17, 2024
Building a new substation1 to 3 yearsRamboll, Dec 17, 2024
Interconnection, Northern Virginia3 to 5 years or longerASHRAE AI Data Center Framework, site planning case studies
Interconnection, TexasTypically 2 to 4 yearsASHRAE AI Data Center Framework
Grid connection in Ashburn5 to 7 yearsDC Byte index, via Data Center Knowledge, Aug 5, 2026
Grid connection against construction2 to 4 years for the grid, about 18 months to buildCotality (data vendor), Jul 31, 2024
A target a land buyer will accept18 to 36 months to interconnection; beyond 36 is speculativeAcres (land data vendor), Jul 27, 2026

Data Center Knowledge suggests stress-testing schedules at 12, 24 and 36 months of delay. Data Center Knowledge, Sep 9, 2026 The site selection checklist puts every step in order, with the evidence document for each.

Mistakes that sink a shortlist

  • Scoring power from a map. A substation nearby says nothing about its spare capacity. Only the utility can answer that.
  • Treating Unknown as average. An unconfirmed criterion is a risk until a document says otherwise. The scorer counts it as a 1 for that reason.
  • Using the composite hazard score. It mixes community vulnerability into a question about your building.
  • Reading the energy rate and skipping the tariff. Minimum bills, exit fees and collateral can outweigh a cheaper rate.
  • Checking zoning once. Moratoriums and ordinance changes arrived in months in 2025. Check again before you close.
  • Ranking sites that fail a gate. A high score cannot rescue a site in a floodway or under a moratorium.

Who runs this site, and what we do for a fee

This site is the site selection desk of Metro Colo Advisory, an advisory and brokerage firm for data center buyers, developers and investors. Reporters at Fortune, Light Reading, Inc. and Al Jazeera have quoted the team that runs this desk.

Shortlist review

We test the sites you already have against the ten criteria, with the documents behind each score, and tell you which one we would pursue and what is still unproven.

Site selection study

From your MW, phases and power date to a scored long list, a shortlist and utility conversations for the finalists.

Colocation or powered shell placement

If leasing beats building, we find buildings with delivered power on your date and negotiate the terms.

Land assessment

For owners: the four screens, the zoning path and what a buyer would ask for, in writing, for a fixed fee.

If your search ends in a colocation lease or a powered shell that we place you in, the facility pays our fee. Site selection studies, shortlist reviews and land assessments are billed at a fixed fee that you sign off on in writing first; no paid work starts without it.

What gets answered first: requests with a target energization year, a MW figure and a budget status. Requests at an earlier stage are answered as well, with a short list of what to pin down before a study pays for itself.

Request a Site Review

Questions about data center site selection

What are the most important criteria for data center site selection?

Power comes first: whether the utility can deliver the megawatts you need, and by when. After that come permitting and zoning, the cost and terms of power, the land itself, natural hazards, tax incentives, fiber, water, latency and labor. The scorer on this page weights power availability at 25 of 100 in its balanced preset and permitting at 15, because those two decide whether a project happens at all. The rest decide what it costs.

How do you weight site selection criteria?

Start from the project type. An AI training campus can tolerate distance from users, so latency barely counts and power climbs to 35 of 100 in our preset. An enterprise or colocation lease leans on fiber and latency instead. A landowner screen ignores tax and labor because a buyer will judge those later. Whatever the preset, the weights must add up to 100, and the scorer tells you whether moving the power weight 10 points would change your leader.

How long does data center site selection take?

The search itself can take months, but the power date sets the real pace. Published ranges include 2 to 4 years for interconnection in Texas and 3 to 5 years or more in Northern Virginia (ASHRAE case studies), and 5 to 7 years for a grid connection in Ashburn (DC Byte, via Data Center Knowledge, Aug 5, 2026). Hyperscalers lock up power and land 24 to 36 months before they need it (DC Byte, Nov 2025).

What is a will-serve letter or load study?

A load study is the utility's analysis of whether its system can serve your new load, what upgrades it needs and when. A will-serve letter is the utility's written statement that it will serve a stated load at a site. Neither is a contract, but a site with one of them scores far higher on power than a site with only a phone call behind it.

What is a large-load tariff?

A rate class for very large customers, usually 25 MW and up, that makes the customer pay for capacity whether it uses it or not. AEP Ohio's data center tariff, in effect since Jul 23, 2025, bills at least 85% of the highest monthly demand and asks for collateral of 50% of total minimum charges from customers without an A-/A3 rating. Those terms now matter as much as the energy rate.

Is the scorer a rating of real places?

No. You supply the scores, using written anchors, and the scorer does the arithmetic. The example sites it can load carry illustrative scores to show how the output reads; they are not ratings of any market or parcel.

How are you paid?

If your search ends in a colocation lease or a powered shell that we place you in, the facility pays our fee. Site selection studies, shortlist reviews and land assessments are billed at a fixed fee that you sign off on in writing first; no paid work starts without it.